Prestige Parklane Current Project Status
Prestige Parklane's current project status shows the site is in the new launch stage. Boundary walls are fenced, digging work is complete, and entrance gates stand ready. Model apartments are also ready for buyers to walk through.
This Prestige STRR project recently received RERA approval, and main construction has just started on site. It was launched officially on 20 September 2026. Possession is set for 31 December 2030, following a five-year build.
Prestige Parklane is a mixed-use township set on 32.26 acres and has 1, 2, and 3 BHK homes from 567 to 1,801 sq. ft. Prices start from ₹56 lakh. Its location is inside KIADB Hi-Tech Aerospace Park. Buyers can check the official RERA website to see the progress status and project details.
What's Happening On-Site Right Now
Early groundwork has already taken shape at this Prestige Devanahalli site. Buyers visiting today can see clear physical progress before towers even begin to rise.
- Boundary walls around the site are fully fenced.
- Digging and earth-levelling work is now complete.
- Entrance gates for the estate are built and in place.
- Model apartments are ready for buyer walkthroughs.
- RERA approval has cleared the way for main construction to begin.
This stage marks the transition from paperwork to physical build, a reassuring sign for early bookers.
Construction Timeline: Sub-Structure Stage
The part of the project that deals with the base work happens before the towers start going up. This stage takes place from October 1 2026 to January 31 2028. This time frame is according to the schedule that was submitted to RERA.
- Earthwork and site levelling
- Foundation footing work
- Retaining wall construction
This stage builds the structural base that will carry all nine towers.
Construction Timeline: Super-Structure Stage
The super-structure stage covers the actual rise of each tower, floor by floor. This phase runs from 1 February 2028 to 30 November 2030.
- RCC or MS framed structure
- Masonry construction
- Doors, windows, and ventilator fittings
This is the longest phase, since it covers the physical construction of all 24 floors across 9 towers.
Construction Timeline: Finishing Work Stage
The finishing stage covers everything needed to make units livable, from utilities to final surfaces. This phase runs from 1 December 2028 to 31 December 2030.
- Electrification, water supply, and sanitary finishing
- Painting and elevation work
- Fire prevention and fire-fighting fixtures
This stage overlaps with the tail end of super-structure work, keeping the overall five-year timeline on track.
How These Stages Line Up With Possession
Each construction stage directly affects the possession date. The sub-structure work has to be done before the towers can start going up. The finishing work must be completely finished before the handover happens. A step-by-step schedule gives buyers a RERA-backed way to follow progress at every stage.
Why Early-Stage Progress Matters for Buyers
Physical progress such as fencing, digging and model apartments shows movement that goes beyond just paperwork. For people who book early, this phase often brings EOI benefits. This includes being able to pick units and getting better floor options.
As construction moves from sub-structure into super-structure over the coming years, buyers can expect visible tower progress to follow this same RERA-filed schedule.
FAQs
Prestige Parklane is currently in its launch stage. The boundary walls are fenced and the digging is complete. The model apartments are ready to view.
Prestige Parklane received RERA approval before the official launch, on 20 September 2026.
The sub-structure work, including the foundation and retaining walls, is expected to be finished by 31 January 2028.
The superstructure work, which includes the RCC frame and masonry, is set to be completed by 30 November 2030.
Possession is scheduled for 31 December 2030 after the finishing work is completed and the five-year build is finalized.