Towers around a pool, for the latest updates on Prestige apartment projects in KIADB Phase 2

Latest updates on Prestige apartment projects in KIADB Phase 2, as of 21 September 2026: Prestige Parklane is registered with Karnataka RERA, EOIs have opened, and the project launches on 25 September 2026 with price sheets starting at ₹56 lakh. Allotment through the survey form starts on 25 September, and tower construction begins on 01 October 2026.

This page keeps a dated record of what has happened, what comes next, and the infrastructure news around the project. Prestige Parklane is the Prestige apartment project in KIADB Phase 2, from award-winning builder Prestige Group.

Prestige Parklane Timeline

Date Update Status
13 August 2026 Building plan DO3-KIADB-00128/26-27/BP approved by KIADB Done
21 August 2026 RERA application acknowledged, ACK/KA/RERA/1251/309/PR/210826/010534 Done
15 September 2026 Registered with Karnataka RERA under PRM/KA/RERA/1251/309/PR/150926/008941 Done
15 September 2026 Expressions of interest opened Done
25 September 2026 Launch and developer price sheets released Done
25 September 2026, 5 PM Survey form opens for allotment priority Upcoming
01 October 2026 Tower construction starts Upcoming
31 December 2030 Proposed completion; RERA registration valid until this date Planned
31 December 2030 Intimation of possession, per the developer price sheet Planned

Update: RERA Registration, 15 September 2026

Karnataka RERA registered Prestige Parklane Phase 1 on 15 September 2026. The registration covers the residential phase of 11.90 acres, with nine towers and 1,788 homes. The promoter is Apex Realty Management Private Limited, and Larsen & Toubro is named as contractor. The enterprise estate on the remaining 20.36 acres is planned as a future phase. Registration means buyer money is now protected by RERA rules, including the requirement to hold 70% of collections in a separate project account.

Update: Payment Plan Announced

The booking sequence runs in five stages. The expression of interest and the survey form cost nothing. Allotment takes 10% of the price, the sale agreement a further 10%, and the balance is paid in 24 date-linked instalments of 3.2% each and a final 3.2% on intimation of possession on 31 December 2030, when the other charges also fall due.

What Is Already on Site

Before tower construction, site works include the experience centre and a model flat. The nine residential towers themselves start on 01 October 2026.

Launch Prices at a Glance

Home Homes Price from
1 BHK Classic 858 ₹56 lakh
2 BHK Optima 391 (both sizes) ₹82 lakh
2 BHK Ultima ₹1.02 crore
3 BHK Aspire 539 (all 3 BHK) ₹1.32 crore
3 BHK Premia ₹1.46 crore
3 BHK Ultima ₹1.64 crore

These prices come from the developer price sheets and are valid till 27 September 2026. They include the car park and the floor rise; GST at 5%, other charges and registration are extra. Each starting price is the lowest-priced home in its configuration, with larger layouts and higher floor bands priced above it, up to ₹1.92 crore.

Infrastructure Updates Around KIADB Phase 2

Project Latest position
Namma Metro Blue Line In August 2026 the full-line completion target moved to March 2028; the Hebbal-to-airport stretch is to open on its own, ahead of the rest
Satellite Town Ring Road The 80-km Dabaspet–Hoskote stretch through Devanahalli has been open since March 2024; the full 280.8-km ring is targeted for 2027-28
Kempegowda International Airport About 20 km from Prestige Parklane, around 29 minutes by road

The nearest planned metro stations for the Aerospace Park area are Doddajala and Bettahalasuru.

Confirmed at Launch: Floor Rise, Parking and Charges

Item What the price sheets say
Floor rise Built into the price through seven floor bands (Ground, 1–4, 5–8, 9–12, 13–16, 17–20 and 21–24), typically adding ₹5–8 lakh from the ground band to the top band
Car parking One car park per apartment, included in the price; Standard, Standard EV or Linked, pre-allotted, and it may sit outside the tower footprint
Other charges ₹415 per sq ft plus a ₹25,000 assessment charge, with GST, paid on intimation of possession: BESCOM and BWSSB, generator, 24 months of advance CAM and the maintenance corpus
Inventory by tower Priced tower by tower and floor band by floor band; it decides which units are open when your turn comes at allotment

Tax Timing for Buyers Taking a Loan Now

Interest paid on a home loan while the building is under construction can be claimed only after possession, in five equal yearly parts. To keep the full ₹2 lakh interest limit, construction must finish within five years of the end of the financial year of the loan. For a loan taken in 2026-27, that window closes on 31 March 2032, after Prestige Parklane's RERA completion date of 31 December 2030.

Launch Week Checklist

  • Confirm your EOI is registered so you receive the survey form, and note that the current price sheets are valid till 27 September 2026
  • Get a home loan pre-approval before 25 September 2026
  • Decide your preferred configuration, tower and facing before the survey form opens
  • Keep 10% of the price ready for allotment and a further 10% for the sale agreement

What to Watch Next

  • Whether prices change when the current price sheets lapse on 27 September 2026
  • The survey form on 25 September 2026, which sets allotment priority
  • Allotment letters and the first sale agreements after the survey form
  • Quarterly construction progress filed with Karnataka RERA after work starts on 01 October 2026

Latest updates on Prestige apartment projects, KIADB Phase 2 FAQs

Prestige Parklane was registered with Karnataka RERA on 15 September 2026 and launches on 25 September 2026, with prices from ₹56 lakh including the car park and floor rise.

Allotment runs through a survey form that opens on 25 September 2026 at 5 PM.

Tower construction starts on 01 October 2026, with completion and possession both set for 31 December 2030.

10% at allotment, 10% at the sale agreement, then 24 date-linked instalments of 3.2% each and a final 3.2% on intimation of possession on 31 December 2030.

The whole Blue Line is now targeted for March 2028, with the Hebbal-to-airport stretch due to open on its own first.

Prestige Group, the award-winning developer with a CRISIL DA1+ grading, is developing Prestige Parklane, with Larsen & Toubro as contractor.