Featured Image of Devanahalli metro stations: the real list, the dates, and a myth

Last reviewed 16 September 2026. In August 2026 the completion target for the whole Blue Line was pushed to March 2028, and the stretch from Hebbal to the airport will now open on its own, ahead of the rest. Plenty of project ads on the Devanahalli corridor claim a home is "ten minutes from Airport Halt metro". Some ads for this very project have said it. No such station is planned. Nor is any station named KIADB.

Both names seem to have spread from one property listing to the next. Neither appears anywhere in Bangalore Metro Rail Corporation's network or plans. This is more than a spelling point. The metro is the biggest single factor in what this corridor will be worth five years from now.

The line under construction

The project is the Blue Line of Namma Metro. It starts at Central Silk Board, passes KR Puram and ends at the airport, and it is being built in two parts.

  • Phase 2A covers Central Silk Board to KR Puram, following the Outer Ring Road.
  • Phase 2B covers KR Puram to the airport: 17 stations over 38.44 km, at a cost of ₹10,584 crore.

Put together, the Blue Line stretches 58.19 km with 29 stations and costs close to ₹14,788 crore. JICA and the Asian Development Bank are funding part of it, while the state government pays for the land.

The stations nearest Devanahalli

Travelling north towards the airport, the final stops are Yelahanka, Bagalur Cross, Bettahalasuru, Doddajala, Airport City at ground level, and KIAL Terminals below ground at Terminal 2. For the KIADB Aerospace Park, the useful ones are Doddajala and Bettahalasuru. Doddajala is usually described as two to three kilometres from the park entrance.

StationPosition on the lineServes
YelahankaInbound of the airport beltEstablished Yelahanka township
Bagalur CrossAirport corridorBagalur node
BettahalasuruAirport corridorAerospace Park, privately funded by Embassy
DoddajalaNearest to the park gateKIADB Aerospace Park, 2–3 km
Airport CityAt gradeAirport business district
KIAL TerminalsUndergroundTerminal 2

A telling detail: private money is involved

Two stations on this stretch are being paid for by private companies. Embassy Group agreed with BMRCL to fund Bettahalasuru station for roughly ₹140 crore. The airport operator took on the 4.95 km section inside the airport, and both of its stations, for about ₹800 crore. Businesses rarely spend their own money on public transit unless they expect it to be built. That tells you more than any official timetable.

So when does it open?

Construction on the line passed the 72 per cent mark in August 2026. Later that same month, the target for the entire corridor moved to March 2028. The Hebbal-to-airport section is now meant to open first, in September 2027. A report on 19 August 2026 suggested even that September date may slip, because work between Yelahanka and the airport is running late. The honest context is that the deadline has already changed three times.

StatedDeadline givenSource
June 2023December 2026, plus or minus three monthsDeputy Chief Minister
February 2024June 2026Governor's address to the legislature
Through mid 2026December 2027BMRCL
Current, August 2026March 2028 full line; September 2027 airport sectionBMRCL

The Deputy Chief Minister has told Blue Line contractors in public that they will get no fresh contracts if they miss dates again. It sounds firm, and it also shows how much pressure the project is under.

How a buyer should treat the metro

Expect it to arrive. The money is committed, the viaduct is up, most stations are built, and private firms have invested. It is a working construction site, not a proposal.

Do not rely on a particular month. If your plan only works when trains run by a fixed date, the plan is fragile. Base your decision on what already operates instead. The airport, both runways and Terminal 2 are running today. So is the Doddaballapur Bypass to Hoskote stretch of the Satellite Town Ring Road, which passes Devanahalli and already charges tolls.

Count the metro as a bonus. Property values along a corridor tend to jump when a line actually opens, mostly within the year around opening day.

Timing against the Parklane handover

For someone buying a flat now, the order of events matters more than any one date. Prestige Parklane received Karnataka RERA registration on 15 September 2026, and its declared completion date is 31 December 2030. On today's schedules, the airport section in September 2027 and the full line in March 2028 both come well before that handover. Even another year of slippage would leave trains running before residents move in. That sequence is the useful part. You would arrive in a neighbourhood already served by the metro, rather than waiting for it after moving.

Why a wrong station name is a warning sign

When a listing names a station that is not real, it shows someone copied details without checking them. That should make you doubt the rest of the listing too: its travel times, its amenity lists, its flat sizes and its possession dates. The check takes seconds. Use it on every project page you read, this one included.

Frequently asked questions

No. BMRCL has no station by that name, now or in its plans. It appears to have spread through property listings copying each other.

The Hebbal-to-airport section is targeted for September 2027, and the complete Blue Line Phase 2B for March 2028. Both dates have shifted before.

The Blue Line. Its Phase 2B section runs 38.44 km from KR Puram to the airport, with 17 stations, and ends underground at Terminal 2.

Roughly two to three kilometres from the park gate. Bettahalasuru station also serves the area.

Phase 2B costs ₹10,584 crore. Including Phase 2A, the whole Blue Line comes to about ₹14,788 crore.

In the past, corridors have repriced around the time a line actually opens, mostly within a year of that date. Treat it as extra upside, not the core of your plan.